Log Record problem

Anu TorMember for 19 years 7 months
Created
1
3
0
When the log record is show " Activity started too early to allow it to finish after the expiration of its predecessor’s lag ". Please advise me, how to solve one?

Thank you.

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Anu,

    This is due to "out of sequence activities" & Finish to Finish Relationship. To avoid this, try to delete the relationship between two activities if it is no longer logic.




Log in or join to reply