Activity Status in the Resource Assignments View

Mark PorterMember for 19 years 2 months
Created
5
2
0
Does anyone out there know of a real easy way of determining the activity status of a particular activity when viewing the activity via the resource assignments view?
The best that I can come up with is either a very convoluted filter or using a global change in the activities view to apply a code which I am then able to access in the resource assignments view, however this then becomes static data which requires the re-running of the global change prior to viewing this data.
Mark

5 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Mark,

    You can view your activity status even without viewing the resource assignments. In Activity Window, you can display Activity Status in your column for each activity, Not Started, In Progress & Completed. Is this what you mean?

    Arnold
  2. 0
    Mark Porter ·
    Hi Arnold,

    I want this functionality in the resource assignments view, not the activity view. Currently I have to either create a filter or run a global change as described earlier
    Cheers
    Mark
  3. 0
    Arnold Puy ·
    Hi Mark,

    YES, I think this is the only way we can do.

    Arnold
  4. 0
    Arnold Puy ·
    Hi L. Dang,

    Great!! How did you paste the image/picture?

    Regards,

    Arnold
  5. 0
    Arnold Puy ·

    Thanks Dang..I will try..

    Regards