Actual bar split
In the Open Standard
Pacifico PallasiguiMember for 22 years 8 months
- Created
- 3
- 2
0
Planners,
Is it possible to split the Actual bar for example I have an activity Excavation Original Duration = 6 days
during status the activity acquired 90% complete with actual duration 33 = days but in reality it acquired only 6 days . Is it possible to suspend - resume actual activity and the actual bar will be divited to the real situation.
Thanks
Jun
Is it possible to split the Actual bar for example I have an activity Excavation Original Duration = 6 days
during status the activity acquired 90% complete with actual duration 33 = days but in reality it acquired only 6 days . Is it possible to suspend - resume actual activity and the actual bar will be divited to the real situation.
Thanks
Jun
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?