Skip to content

Cost Units Unlinked on P3

Brian BeckMember for 19 years 1 month
Created
3
2
0
Is there a way to unlink unit cost percent complete from the performance percent complete?

This would be similar to unchecking the cost unit box in P5.

3 replies

Oldest first
  1. 0
    Brian Beck ·
    Ok, figured out what I want to do, but I need to make a global change for this.

    Can anyone help me with this?

    I need to make a global change that unchecks the box when you go to options / tools / autocost rules, Link remaining duration and schedule percent completes
  2. 0
    Brian Beck ·
    Bump
  3. 0
    Arnold Puy ·
    Hi Brian,

    I think you need to be more specific in your post #2 that’s why no one answer your question or maybe you can cite an example to make it clear.

    Regards.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?