Update as scheduled
In the Open Standard
Jim SandersMember for 18 years
- Created
- 9
- 1
0
Hi
I’ve recently started using P6 rather than MS Project and I want to know how I can progress an activity in line with its plan. For example, I may have an activity representing the project manager overhead on a project and on a weekly basis I just want to increment the progress up to the data date. I don’t want the end of the activity to move out and the duration % complete should increase accordingly. Essentially doing the same as the MSP ’Update as Scheduled’ button on the tracking toolbar.
I’ve tried using the Auto Compute Actuals flag with Apply Actuals but the Activity Finish moves out.
What am I missing?
Cheers
Jim
I’ve recently started using P6 rather than MS Project and I want to know how I can progress an activity in line with its plan. For example, I may have an activity representing the project manager overhead on a project and on a weekly basis I just want to increment the progress up to the data date. I don’t want the end of the activity to move out and the duration % complete should increase accordingly. Essentially doing the same as the MSP ’Update as Scheduled’ button on the tracking toolbar.
I’ve tried using the Auto Compute Actuals flag with Apply Actuals but the Activity Finish moves out.
What am I missing?
Cheers
Jim
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?