Resource Dependent Planning
In the Open Standard
Oliver MellingMember for 19 years 5 months
- Created
- 3
- 2
0
PPlanet,
On a plan i have several activities with resource dependent activity type, fixed units/time, with a primary resource that only work a 3 day week.(Mon-Wed)
When i move the data date to Tuesday, for an unstarted 3 day task i expect the activity to extend in duration so that the days work that was planned for Wednesday moves to Monday, but what actually happens is that the finish date move to the Thursday.
This seems wrong to me as i thought, where an activity is resource dependent, the work will be scheduled against the resource calendar of the primary resource?
Has anyone come across this before?
On a plan i have several activities with resource dependent activity type, fixed units/time, with a primary resource that only work a 3 day week.(Mon-Wed)
When i move the data date to Tuesday, for an unstarted 3 day task i expect the activity to extend in duration so that the days work that was planned for Wednesday moves to Monday, but what actually happens is that the finish date move to the Thursday.
This seems wrong to me as i thought, where an activity is resource dependent, the work will be scheduled against the resource calendar of the primary resource?
Has anyone come across this before?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?