problem with dates and calenders

Punit KhuranaMember for 18 years 1 month
Created
4
5
0
Dear all,

I am a biginner. while feeding a chart, I have successfully entered obs/eps/wbs and activities with their time and relation ( pred and successors ), ciritical path created. Now How to adujust calender for the whole project and how to ascertain that what I am doing is ok. for a while I was out of touch after doing my course and now I have started it again. Help help I am in net of network...

4 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Punit,

    Create a new calendar considering holidays & non-working days and assign the new created calendar to your activities.

    You can create more than one calendar and likewise, you can assign more than one calendar to your project but not to your activities.

    Regards.
  2. 0
    Punit Khurana ·
    thanks Arnold ,
    I am trying to work on what u told and your earlier replies.

    Shall be in touch.

    Punit


  3. 0
    A D ·
    Try to use global change to change calendar, rather than doing one by one.
  4. 0
    Arnold Puy ·

    In addition to Rav’s suggestion. You can use the Fill Down or "CTRL+E" to change the Calendar. But before doing this, display the calendar in your Column Activity Module and select the Calendar you wanted to assign.

    Regards.