Cumulative Early and Late Curves

Ernesto MontalesMember for 24 years 6 months
Created
2
1
0
Hello.

Just want to know if anyone has experience when they produce a cost loading report at some point when you plot the data coming from the report writer on P6 the curve the early cumulative curve is less that the late cumulative curve on some time period. Is this possible?

2 replies

Oldest first
  1. 0
    Ian Adan ·
    I guess you have negative float on some of your activities.
  2. 0
    Rama Krishnan ·
    If you have copied activities from another project , constraints of previous project are also copied such as project finish by date or activity’s must complete by.
    These could introduce unwanted negative float

    Rama