Copy and paste activities in P5

Mohsen MMember for 18 years 7 months
Created
3
1
0
Hi All,

I really miss the easy way of copying and pasting in P3 allowing you to change the Activity ID before pasting by using suffix or prefix, applying increment, etc.

How that can be done in P5?

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Mohsen,

    You can do this by changing first the prefix, suffix & increment in project detail --> default tab --> auto-numbering defaults and uncheck the "Increment Activity ID based on selected activity" if you don’t need to copy the existing Activitiy ID.

    Try this.

    Arnold
  2. 0
    Mohsen M ·
    Hi Arnold,

    Thanks for your answer,it was exacly what I was looking for.

    Cheers,
    Mohsen
  3. 0
    Arnold Puy ·

    You’re welcome.