List of Activities, their predecessors have been met

Roozbeh TaheriMember for 23 years 5 months
Created
4
2
0
Can you please help me in P5, how can I filter activities which their predecessors have been met . Specially for FS relationships, I wand to have a list of activities which status of their predecessors are completed.

4 replies

Oldest first
  1. 0
    Gordon Blair ·
    Probably the quickest way is to filter for all those activities whose remaining start = the Data Date (they have nothing holding them out).

    Hope this helps,

    Gordon
  2. 0
    Arnold Puy ·
    Hi Roozbeh,

    Try this Filter:

    Activity Status "equals" Completed
    Predecessor "is not equal to" blank

    Note: Blank means do not put any value.


    Arnold
  3. 0
    Roozbeh Taheri ·
    Hi Arnold,

    I tried the filter and it lists all the activites which have a predecessor (their predecessor is not blank), and are completed, while I need list of activites as follow:
    1 - Their predecessors are complete.
    2 - They are not started.

    Also Gordon’s suggestion does not work in my case, because there are some out-of sequence completed activies which their successors’ start date is not equal to data date.

    Is there any other idea if I can filter "not started" activities which their predecessors status are "completed"
  4. 0
    Arnold Puy ·
    Hi Roozbeh,

    Try these Filters:

    (Any of the following)

    Where Predecessors "equals" 100
    Or Activity Status "equals" Completed


    HTH.

    Arnold