Hammock ’line’ or ’activity’

Jonathan WardMember for 19 years 8 months
Created
9
2
0
hello all,

I am a P3 user who has very recently moved over to P3e, all seems to be going well and i think i like the new interface more than P3,, my question may seem quite simple, but i would appreciate some help all the same.
I have a group of activities all sharing the same coding in the WWBS,, i would like to represent the start and finish of all of the group with what i refer to as a ’hammock’ activity that sits at the top of the group.

many thanks

Jon

9 replies

Oldest first
  1. 0
    Jonathan Ward ·
    i believe i am asking about Level of Effort??
    many thanks
    Jon
  2. 0
    James Shimmon ·
    Jon
    Add in a new activity in the WBS leg and change the activity type to WBS Summary - link with SS to the first chronological activity and FF with the final chronological activity, WBS Summary will autmoatically change dates if any of the detail underneath changes

    Shimmo
  3. 0
    Jonathan Ward ·
    Shimmo,, your the man
    cheers
  4. 0
    James Shimmon ·
    no problem, you can also run filters when you do printouts which will filter these off as I have found people can get confused by them and question why they are there
  5. 0
    Steven Oliver ·
    It isnt necessary to "link" a WBS Summary activity
  6. 0
    Ali Farhat ·
    Steven is right, you do not need to link the WBS summary. you only assign the WBS and it will give its summary
    Level of effort is completely different, it is a flexible activity where its duration depends on its successor and predecessor. Level of efforts need to be linked
  7. 0
    Jonathan Ward ·
    thanks for that info Gents,, so just for clarity, in my instance, i really want one activity bar at the very top of the ’group’ that details the START of the first activity and FINISH of the last activity (all of the activities inbetween are logic linked),, what Activity Type shoud I go for?? Level of Effort or WBS SUmmary??
    once again, many thanks for all info posted

    regards
    Jon
  8. 0
    Steven Oliver ·
    WBS Summary
  9. 0
    Ali Farhat ·
    Jon, you dont use the WBS summary for this case unless your group is a COMPLETE WBS. The start date of WBS summary is the start date of the FIRST activity in the WBS and the finish date is that of the LAST activity of the WBS even is the activities in reference are not displayed in your layout.
    if you need to view the summary of any group in your layout (whether having the same code, wbs, or any other criteria) simply check the option in your group and sort window that says: Show group totals.
    If you want to display this total on Gantt chart, right click on the chart -> bars -> click on the "Summary bar"