Locking in open-started activities before scheduling
In the Open Standard
Minnaar FourieMember for 19 years 4 months
- Created
- 5
- 3
0
I have and xer file that is a client project (call it Proj A) that has been imported in P6. This project originally had relationships to external projects but after importing these links no longer constrain the activities in Proj A. The dates will be reflected as it was when linked to the external projects. When I schedule, the activities that are now open-started (ie no predecessor) move to my data date loosing their original dates.
How can I schedule the newly imported project whilst keeping the original start dates in tact for the open-started activities? Is there a setting of some sort or will I have to manually put a constraint into each of the open started activities?
How can I schedule the newly imported project whilst keeping the original start dates in tact for the open-started activities? Is there a setting of some sort or will I have to manually put a constraint into each of the open started activities?
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?