Skip to content

Primavera Digger

Anu TorMember for 19 years 7 months
Created
1
1
0
Good morning,

Anybody know the best compare software to P3 between original sch. and updating one ane. Where can I find and dowload?

Thank you,

1 reply

Oldest first
  1. 0
    Ronald Winter ·
    For comparison of P3 schedule updates, you have two choices; Claim Digger (sold my Primavera) and Schedule Analyzer (sold by my company, Ron Winter Consulting LLC.)

    A fact sheet on Claim Digger may be found on the Primavera website at https://www.primavera.com/files/datasheet/claim_digger_datasheet.pdf but for the life of me, I cannot find anywhere on the Primavera.com website that says it is still for sale. I wonder if this is Oracle’s way of saying, "Hellow"?

    The Schedule Analyzer main page is at www.ScheduleAnalyzer.com. Schedule Analyzer is too large to download, but overseas mail is an option.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?