Activity ID NUBERS

Carlos DominguezMember for 17 years 11 months
Created
7
3
0
Hello PPP’s

can anyone tell me, if for example i use activity id numbers
such as A9910,9920,9930 and my incrments are by 10, why when i get to A10000,primavera sorts the A10000 as the first activity rather than putting it as the last activity
when i sort by activity ID ?

7 replies

Oldest first
  1. 0
    Ali Farhat ·
    when you combine a text with number, P6 treats the numbers as text, the "1" in A10000 is less than "9" in A9910. this applies to all the software,
    the trick is to use a "0" always before the number.
    2 is sorted AFTER 10
    but
    02 is sorted BEFORE 10

  2. 0
    Carlos Dominguez ·
    Ali,

    Thank-you so much for answering that question, so what do i do now that i have a A9990 , to correct it for A10000. how can i fix this ? because i need it to go after A9990....
  3. 0
    Arnold Puy ·
    Hi Carlos,

    Why don’t you try to add "0" right after "A" by using global change or maybe you can do one thing, instead of ascending use descending. But, the problem is all your activity id will be affected.

    If you are interested with inserting 0 after A try this parameter in global change. But before doing this backup your project.

    Where
    Activity ID "does not contain" A1

    Then
    User_text1 "=" SubString(Activity ID,2,6)
    Activity ID "=" A0 "&" User_text1

    Just let me know, so that I can assist you.

    Regards,

    Arnold
  4. 0
    Carlos Dominguez ·
    Arnold,

    Thanks a lot man i appreciate it i think i can get the global change done that should help i tiered to do the global change earlier but i had the wrong formula in there so i will try this and see how it goes..


    thank you and have a merry christmas and a happy new year
  5. 0
    Nestor Principe ·
    Carlos,

    Sometime, you don’t want to change the activity ID if the programme has already been submitted or approved.

    If this isthe case, maybe sorting it by a custom data item will help.

    Create a custom data item, assign value for every activity according to the intended order within the group (organization or WBS).

    Yes, I agree, the best solution is to edit the activity ID.

    Cheers
  6. 0
    Mark Chapman ·
    After A99990 use B00010
  7. 0
    Glenn Douglas ·
    Nice one Mark, no-one saw that coming.