need some SQLSERVER guru advice.

Mimoune DjouallahMember for 20 years
Created
0
1
0
Hi planner and happy New Year.

I am using SQLSERVER database connection to get live data from PM6 to excel, it works as a charm (Imho it is enough reason to upgrade from p3 to P6), I have to thank here emma for sending me a sample spreadsheet.

Now what I need to do is to make a presentation, showing tasks organized by wbs code, the tricky part is that I can only get wbs attached to activities but not that parent WBS.
Something like that

TANKS ERECTION
Tanks with a fixed roof
Demineralised water tanks
TANK.FIXED.DEMI.01 Erection of 6000 M3 demi water tanks.

For now all I can get is

TANK.FIXED.DEMI.01 Erection of 6000 M3 demi water tanks.


Any idea ?


Mimoune

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?