What is "Activity Resource Assignment" ?

Armana JonesMember for 17 years 9 months
Created
5
2
0
Dear friends,
I’m a new user of P6 and in somedays I confused in finding the meaning of "Activity Resource Assignment"? Is it Activity, Resource or other?

Thanks.
Armana

5 replies

Oldest first
  1. 0
    A D ·
    It means resource assigned for an activity. There is no such specific option/tab in P6 for activity resource assignment.

    There r two things to watch for resource assignment:

    1. Go to Edit --> User Preferences --> Calculations.
    The calculation tab has two options:
    a) With the first option, each resource hours are calculated independently.
    b) In second option, total no. of hours assigned to an activity will stay constant and sunsequesnt resources are added or removed from an activity. However, this option doesn’t work, if activity type is FIXED DURATION and Units/Time.

    2. Resources can be assigned to the same activity more than once. I forgot now where this option is, but may be somebody from teh forum can help on this.

    Wish u a very happy new year

    Cheers,

    Rav
  2. 0
    Arnold Puy ·
    Hi Rav,

    Resources can be assigned to the same activity more than once. This option can be found in the Project Detail --> Resources Tab under Resource Assignments.

    Regards.

  3. 0
    A D ·
    Thanks Dear,

    Thanks a ton
  4. 0
    Arnold Puy ·

    You’re welcome Rav.

  5. 0
    Armana Jones ·
    Thanks a lot everybody.