Update on P3e

Leonard OkpalekeMember for 18 years
Created
4
2
0
Can someone advise me on what to do? I have updated my project on P3e but realized that all tasks in progress are still at 0% physical complete.

4 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Leonard,

    Physical % complete is users manual input. You need to feed the % complete of each activity or calculated based on activity’s weighted steps.

    Regards.
  2. 0
    Leonard Okpaleke ·
    Thanks Arnold for the info. I noticed after the manual update that on the earned value table, that budgeted labour units and remaining labour units are the same, even when the task 90% physical complete. Has this got to do with my setting.

    I have done my calculation using FTC=Budgeted-EV where Act=0, But have found it difficult to correct on my plan.
  3. 0
    Arnold Puy ·
  4. 0
    Arnold Puy ·
    Hi Leonard,

    First of all, you need to set actual start to your activities then change the finish date, after that press F9 for schedule update & change the data date.

    Now, try to notice that your actual units this period and actual units are the same when "link actual and actual this period units & cost" is tick, under the project deatils --> calculation tab. Likewise, this is only occur when your "Recalculate actual units and cost when duration % complete changes" is tick. Because, your calculation is based on duration % complete, performance % complete & activity % complete.

    When it happens that your "Recalculate actual units and cost when duration % complete changes" is untick and you are trying to update your activities based on Physical % complete. Then you should have to input the actual units manually.

    HTH.

    Regards,

    Arnold