P6, Remove resource from many activities & add another
In the Open Standard
Abeer MahmoudMember for 18 years 3 months
- Created
- 5
- 3
0
Dear All,
i have 3 resourecs type 1, 2 & 3 were assigned to 30 Dear All,
I have 3 resources type 1, 2 & 3 were assigned to 30 activities now i need to remove resource type 3 from all activities and add instead of it resource type 4 talking into consideration the project WBS includes 6 levels and 100 activities.
I prepared a filter included only activities which need to modify resources and exported to excel sheet but when i opened excel file I found it included all 100 activities and ignored my filter.
So can any body help me by a shortcut way by excel sheet solve this problem.
Regards,
Abeer
i have 3 resourecs type 1, 2 & 3 were assigned to 30 Dear All,
I have 3 resources type 1, 2 & 3 were assigned to 30 activities now i need to remove resource type 3 from all activities and add instead of it resource type 4 talking into consideration the project WBS includes 6 levels and 100 activities.
I prepared a filter included only activities which need to modify resources and exported to excel sheet but when i opened excel file I found it included all 100 activities and ignored my filter.
So can any body help me by a shortcut way by excel sheet solve this problem.
Regards,
Abeer
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?