Skip to content

P6; Reallocate Resource Unit Price

Abeer MahmoudMember for 18 years 3 months
Created
2
2
0
I have a serious problem; at P6,I have resource cost $5 per hour I modified it to $10 per hour and when I go back to activities it is not reallocate the resource unit price it keep it with $5 not $10 how I solve this problem.

Regards,
Abeer

2 replies

Oldest first
  1. 0
    osama Eltantawy ·
    Hi, Abeer
    you have to go to
    Tools then "recalculate assignment costs" then recalculate
    but also insure also that in the resouces layout that the option "calculate costs from units" in details tab is checked for this resource you have changed unit price.

    Please inform me the result.

    thank you

    Osama
  2. 0
    Abeer Mahmoud ·
    Dear Osama,

    It is worked thanks very much Osama I really appreciate your support.

    Regards,
    Abeer

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?