Importing P5 project into Contractor 6.1 problems
In the Open Standard
Mike FentonMember for 18 years 3 months
- Created
- 1
- 3
0
When I import a P5 project (xer) into Contractor 6.1, the budgeted total costs are modified. They should be the same values. There are no other problems, eg: activities, logic, durations are all correct. It seems to be only the budgets that are an issue. Has anyone had this problem and worked out a solution?
1 reply