Skip to content

Importing P5 project into Contractor 6.1 problems

Mike FentonMember for 18 years 3 months
Created
1
3
0
When I import a P5 project (xer) into Contractor 6.1, the budgeted total costs are modified. They should be the same values. There are no other problems, eg: activities, logic, durations are all correct. It seems to be only the budgets that are an issue. Has anyone had this problem and worked out a solution?

1 reply

Oldest first
  1. 0
    Mike Fenton ·
    Problem solved!!!!
    The project I was importing had a currency based in Australian dollars and the project I was importing into was based on US Dollars. This currency exchange was set to 1.7964 so my original project of say a budget - $100M was showing up as $55M when imported.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?