Necking and printing suspended tasks
In the Open Standard
David PodmoreMember for 20 years 5 months
- Created
- 1
- 2
0
I have searched the forum for references to this odd behaviour and I don’t seem to be alone....
I have set my all my bars to neck in "Activity non-working intervals" to demonstrate when the work stream was interrupted due to outside influences - a hiatus if you will.
When I print preview and the Gantt is small enough to fit across one page or I force it fit, it fails to render the necking (nor does it come out on the printer). HOWEVER, if you force it to fit across more than one page or it’s naturally that big, low and behold, the necking appears.
I don’t want to show "Calendar non-working time" so this is NOT selected.
I am about to beat the computer with an MSP2003 manual!!!!
I have set my all my bars to neck in "Activity non-working intervals" to demonstrate when the work stream was interrupted due to outside influences - a hiatus if you will.
When I print preview and the Gantt is small enough to fit across one page or I force it fit, it fails to render the necking (nor does it come out on the printer). HOWEVER, if you force it to fit across more than one page or it’s naturally that big, low and behold, the necking appears.
I don’t want to show "Calendar non-working time" so this is NOT selected.
I am about to beat the computer with an MSP2003 manual!!!!
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?