budgeted total cost and cost percent complete becomes zero after using update progress command
In the Open Standard
Kai AbMember for 6 years 10 months
- Created
- 9
- 5
0
after using "update progress" command in the tool tab, the budgeted labor cost, budgeted material cost, budgeted non labor cost, budgeted total cost and cost percent complete of each activities that have been selected or updated became zero but the duration percent complete is updated and not zero. Anyone know how to fix this problem? im just new in using primavera. I updated my sample project after 4 days from the start date of the project.
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?