Add new Resource to an Activity
In the Open Standard
Philip RichardsMember for 22 years 9 months
- Created
- 2
- 1
0
When i add a new Resource to an existing activity which already has stored period performance against other resources, the new resource is given a period performance equal to the sum of the existing period performances (Total Period Performance for that activity doubles).
This does not happen all the time. It is hit and miss.
I cannot find a setting relating to this.
Does anyone have any suggestions Please
This does not happen all the time. It is hit and miss.
I cannot find a setting relating to this.
Does anyone have any suggestions Please