WBS duration

Sonia RoseMember for 17 years 11 months
Created
2
3
0
Hello Planners,

I’m missing an option for WBS summary activity duration. My Project calendar is 5 working days per week but the duration displayed in the WBS level is based on calendar 7 working days per week.
Can anyone help me please

2 replies

Oldest first
  1. 0
    A D ·
    Thats because WBS Durations are based on global calendar and not project calendar.

    Ur global calendar must be set for 5 days a week. The issue is still not resolved by primavera and is on the list.

    Cheers,

    Rav
  2. 0
    Sonia Rose ·
    Thanks Raviraj