Checking access in P6

Barry FullartonMember for 17 years 10 months
Created
6
31
0
Guys

How can one check who had been into a P6 project

Just to give you a background, we have various different Projects on our P6 , and different Planners on different Projects, How does one check who has been into your project or accessed your project historically


Thanks

6 replies

Oldest first
  1. 0
    David Kelly ·
    You can’t.

    There is no "last used" functionality.

    Any such test/trigger would have to be at the Oracle or Operating System level.

    We have checked this up to and including version 6.2.

  2. 0
    A D ·
    If its true, then its a big mess by Primavera.....

    How to track it then... At least even by log-in details

    Just curious, what admin guys must b doing and y it has not been included frm last so many years?
  3. 0
    Barry Fullarton ·
    Guys

    it is just that , any one can then access the program , and should he make changes , in error, you dont know who has been in your prgram , i find this a major flaw in P6
  4. 0
    David Kelly ·
    There are some "last changed by" flags in the database - but no "last used by"
  5. 0
    Sandy Matheson ·
    Is ther any way to check who is currenty in a project? We have integrated schedules with users in several locations. Any way to know who is also accessing a project?
  6. 0
    David Kelly ·
    The "File:Open" dialog has a "users" button that tells you who is currnetly in the project

Log in or join to reply