Progress checking as Physical
- Created
- 5
- 5
Hi,
I have a problem in the progress checking in P6. I have selected the physical progress and duration type as fixed duration & units.
After updating an activity with 50% progress, the peformance percentage of the activity can be calculated with EV method. but the problem is, if i change the finish date of the activity (based on site forecast), by keeping the same data date, the actual labour units will turn to zero, accordingly the actual labour cost. But still the physical progress of 50% and EV calculation remains the same. How to keep the actual labour units as it is even with the change in finish date. because of this actual and remaining cost column is affected.
Please advise, if i miss something to make it correct.
Thanks
Kannan
5 replies