Original Dur Vs Remaining Dur

Mohsen MMember for 18 years 7 months
Created
3
3
0
Hello PP Friends,

I have two projects imported form MSP into P6. The problem is this, when I change the original duration of activities that are scheduled to start in the future the remaining duration does not change accordingly. From the “Projects” view and under “Calculations” tab I have “Reset remaining duration and units to original” selected. Can anyone help with that please?

Cheers,

Mohsen

3 replies

Oldest first
  1. 0
    David Kelly ·
    Check "link budget and at completion for not started activities" in the calculations tab.....
  2. 0
    Dieter Wambach ·
    Mohsen
    ... and "Link budget and..."? Did you recalculate?

    Regards
    Dieter
  3. 0
    Mohsen M ·
    Hi David & Dieter,

    Thank you for your help with this matter. It’s all good now.

    Cheers,

    Mohsen