Anybody got a clever global change to delete resources that have been assigned to activities. I’ve inherited a programme and want to delete all the existing resource assignments and then add my own. 3000+ activities so i really dont fancy doing this one manually, and i’m not yet that up to speed on exporting and importing in excel.

Thanks in advance for any help

7 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Glen

    Global Change doesn’t work in this case I’m afraid.

    To do it manually isn’t that effort as it sounds.

    Open your programme --> view "Activities" --> cursor into table area --> push right button --> select "Group & Sort" --> by resource id --> on the right border of your P6-Window you see an icon "assign resources (no 7 from bottom) push --> push "Display: All Resources" --> filter by --> current project’s resources --> then for each group in main window select all activities --> select that particular resource in the assign window --> push icon delete.

    It took me more time for writing than you’ll need to delete all assignments.

    Hope that helps

    Dieter
  2. 0
    David Podmore ·
    Nice one.

    If your replacement resources are a one for one replacement for the existing ones (or in some cases at least) you can use Global Update. Just configure the tool to:- where resource = resource"x" make resource = resource "newx"
    That way you get the new resources in where you want them. Even if it’s only half of the 3000+ tasks it could save you a load of time.

    Only a thought... :o)

    David
  3. 0
    Glen Staunton ·
    Dieter thanks for replying. That approach would be perfect, except there are other users within my project who use some of these resources. I’m pretty sure if I delete them I’ll be undoing some one elses hard work. Is it possible to do as you suggest but limit it to a specific filter within my project?

    Thanks

    glen
  4. 0
    Glen Staunton ·
    Hey i’ve already had a go highlighting activities i’ve filtered and it seems to work... So thanks a million
  5. 0
    Dieter Wambach ·
    You’re welcome
  6. 0
    Karim Mahgob ·
    Go to Resouce Assigment window---->mark all ---> then delete.

    it’s easier to delete all resource in one shot
  7. 0
    Sudheerkumar Gurram ·
    Hey I am sudheerkumar membership (10090) from Abu Dhabi, I want to know the advancement in P6.0 from p5.0.

    And also, could please mail me P6.0 USER MANUL in PDF please.

    skgurram59@yahoo.com
    sudheerk@trsa.es

    Thanks