How to show Progress Line in P6?

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    In P6 there is no progress line. You can show some varances (group by, filter, display within the table) and of course BL-bar vs. actual bar.
  2. 0
    Peter Nicol ·
    Dieter, actually doesn’t the Percentage complete option for bars show the progress on the bar chart ?

    I think that is he is after

    - Peter.
  3. 0
    Dieter Wambach ·
    Peter

    You can show the progress as bars - as you said.
    My impression was that he was missing the progress line of P3.

    Regards
    Dieter