Resorce Loading

Randy TaylorMember for 17 years 7 months
Created
1
2
0
Under Enterprise Resource, I have dedicated my price/unit as internal cost and have set up price/unit2 as reveune. Is there a way, after going back to the activities screen to switch from viewing the cost detail to view the revenue detail. Please advise.

1 reply

Oldest first
  1. 0
    Valerii Buturlakin ·
    Hi, Randy

    I don’t know if your question still actual.

    If "yes", In that case you must assign resourse into activity twice. Then you can see internal cost and revenue.

    Best regards,

    Valerii