Does anyone know how to retain actual costs when you are using "Physical" for % Complete Type? Whenever we insert a remaining duration it zeros out the actual cost.

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    James

    Yes.


    For your information: Check the parameter settings in view "Projects" under tab "Resources" on the right.

    Regards
    Dieter
  2. 0
    James Braghini ·
    Your the man as usual.

    Thanks,
    James B.