Skip to content

In P6 Formating Axis Options are possible.

Mohammed WasiuddinMember for 17 years 7 months
Created
1
3
0
Hai , I am wasim could anyone assit me on the following issues please:
1.)Is this possible in P6 that, when we compute the physical/Duration % value will it automatically upadate the cost % complete.If so what are the right combinations should be?

2.) Is this possible in p6 that,from the cost usage profile or from the resource usage profile especially when we are using histograms, could it possible to change Axis options same as like Excel Format Axis Options.

Thanking you.

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Mohammed,

    1. It is possible for Duration % and Cost % complete will be automatically updated if you mark the checkbox next to "Recalculate Actual Units and Cost when duration % complete changes" in Project workspace --> Calculations Tab.

    For Physical % complete can either user entered or calculated from the activity’s weighted steps.

    If you want that Physical % complete will be equal to your Duration % complete, you need to run the global change.

    2. It is possible if you will try to change the "Calculate Average" depending in your "Divide interval totals by:" However, the information for your quantity/cost calculation pop-up displayed will also change due to "Calculate Average" you input.

    HTH.

    Arnold

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?