Is Activity Usage Profile Options is Editable ?

Irfan KhanMember for 17 years 3 months
Created
9
5
0

 

hi to all experts,
 
here i am searching the way to edit some containts which is under "Activity Usage Profile Options".
 
example  
 
Exist text  : Baseline 
                 : Budgeted 
                 : Actual
                 : Remaining Early
                 : Remaining Late 
 
here can i change these text to my desired text i.e. inspite of Baseline i want Civil ?
 
Because this examples i saw in my friend's laptop he is using the same version of Primavera P6 v.7.
 
Can anyone solve my problem pls.

9 replies

Oldest first
  1. 0
    Daniel Limson ·

    Irfan,I am afraid this is not

    Irfan,

    I am afraid this is not eiditble and this not the place to do it, if you want Civil Works Labour Profile, you need to filter all civil works, you need to assign activity codes for civil works or you can filter civil works under a unque WBS code.

    Best regards,

    Daniel

  2. 0
    Irfan Khan ·

    thanx Daniel Limson, m agree

    thanx Daniel Limson,

     

    m agree with u, but 1 of my friend i dont know how he edited that text field.

    i surprised to saw that & that's why m searching the ways to edit that text.

     

    thanks................

  3. 0
    Raymund de Laza ·

    Yes you can, that's possible

    Yes you can, that's possible .... but......??? :>

  4. 0
    Irfan Khan ·

    @ Raymund de Laza but

    @ Raymund de Laza but wht....?

  5. 0
    Raymund de Laza ·

    Irfan,Why was your friend

    Irfan,

    Why was your friend does'nt like to share with you what he have? Is he/she a friend Indeed?

    You have a friend that can solve the problem, why are you asking others to solve your problem....

  6. 0
    Irfan Khan ·

    dear friends, please find

    dear friends, please find attached an example which is showing the modification of legends in Activity Usage Profile Options.

    Would anyone share with me that how to edit legend in Activity Usage Profile Options ?

  7. 0
    Irfan Khan ·

    dear friends, please find

    dear friends, please find attached an example which is showing the modification of legends in Activity Usage Profile Options.

    Would anyone share with me that how to edit legend in Activity Usage Profile Options ?

  8. 0
    Raymund de Laza ·

    Irfan, That is a stack

    Irfan,

    That is a stack histogram.... that's so simple to do....

    here is the image....

    would rather send through your email....

  9. 0
    Irfan Khan ·

    thanx Mr. Raymund de Laza for

    thanx Mr. Raymund de Laza

     

    for to clear my all doubts....:)