Ali FarhatMember for 17 years 11 months
Created
4
3
0
Hi everyone,
Can anyone please give some examples of how Cost accounts are used in P6?
Regards

4 replies

Oldest first
  1. 0
    R. Catalan ·
    Ali,

    Assuming you’re working on a high-rise building project, and you linked your cost accounts with resource assignments, then you can use cost accounts to track activity costs.

    Sample:
    You can group/sort activities by floor and then run P6 filter options using cost accounts to track total costs in period under the same cost category (by CSI Division, i.e concrete works, finishes, etc.). This tool is very helpful in doing earned-value analysis.

    Hope this will help.

    R. Catalan
  2. 0
    Ali Farhat ·
    Thanks Mr. Catalan,

    Cant I reach the same result if I categorize my resources in divisions (using a father resource for each division) and then group the resource assignments?
  3. 0
    Khuong Do ·

    Hi, I write an article

    Hi,

    I write an article regarding What is Cost Account in Primavera P6 used for? If you're interested, kindly read it here https://doduykhuong.com/2016/10/08/what-is-cost-account-in-primavera-p6-used-for/

  4. 0
    Zoltan Palffy ·

    one thing that you can do is

    one thing that you can do is to create cost codes for your activities and assign them to the resource for the activity and you can have your accounting system push actual data to p6 in the form of an excel file.

    You can track your budgeted and actual labor that way 

Log in or join to reply