Event Intercepted

Arnel LagumbayMember for 18 years 1 month
Created
10
3
0
Hi all,

"An Application event has been intercepted pls note the

event code for reference DSECL-0549-E". and after P6

closed.Somebody here encounter this kind of problem?

To those PPp that can share...Thanks in advance..


Regards,
Rnel

10 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Arnel

    Within that window you have the choice between three buttons - select "More". Within the following window you’ll get more information --> "Copy" --> paste here.

    Or ask Primavera or your local dealer. They should have a reference list for those error codes.

    Regards
    Dieter
  2. 0
    Arnel Lagumbay ·
    Thanks Dieter,

    This happens twice in my P6,but now its working fine.I will note it, if it happens again.


    Regards,
    Arnel
  3. 0
    Montasir Abdelhalim ·

    HI HERE IS THE COPY OF THE

    HI

     HERE IS THE COPY OF THE MESSAGE OF THE SAME ISSUE: 

     

    "*****************************************************

    *                EXCEPTION  REPORT                  *
    *****************************************************
    Date:          13-Oct-17 
     
    Executable:    PM.exe
    Application:   Primavera Project Management
    Event Code:    AVAA0-1935-0
    Message:       
      Access violation at address 00830C9C in module 
      'PM.exe'. Read of address 00000008
     
    Context: 
      1: TfrmMain.actReportsReportsExecute
      2: TfrmWizImport.RunCheckInWizard
      3: TfrmMain.actCheckIn1Execute
      4: TCFormManager.SetToolbar
      5: TfrmLogin.FormCreate
      6: 
      7: 
      8: 
      9: 
      10: 
     
    Detail: 
      Type:        EAccessViolation
      Object Type: TCUltraButton
     
     
    Components
    ==========
    ORI: ORI Win32 #
    ORI/DB: PMDB,0600.0011.0001.0002
    IMG: IMG Win32 #1000
     
    System Info
    ===========
    Username: user   Hostname: USER-PC
    OS Version: Windows NT ver 6.1, build 7600,  (Intel Pentium)
    "
     
     
     
    PLEASE KINDLY HELP ME TO FIX THIS SO I CAN SEE MY REPORTS.
     
    THANKS 
     
    MONTASIR
  4. 0
    Montasir Abdelhalim ·

    HI

    HI 

  5. 0
    Santhosh S ·

    Primavera 16.2Error while

    Primavera 16.2

    Error while scheduleing

    DB : SQL

    Error :

    an application event has been intercepted. please note the event code for reference 

    Event code  : SSFII-0822-6

     

  6. 0
    Zoltan Palffy ·

    Follow steps below to fix the

    Follow steps below to fix the issue:
    1. Click F9 to get the Schedule window.
    2. Check the Log to file option to save schedule details.
    3. Schedule the project.
    4. View the log, then fix the loops reported in the log file.

    Workaround:

    By default P6 only checks 10 loops per schedule.In order to allow more loops in the project, set a PM.ini named MaxLoopsToReportCount under Schedule option and set it value which suits the required loops.  It should not be too much so that schedule will take time to process so many loops.

    [Schedule]
    MaxLoopsToReportCount=-1 (this setting will show all loops)
  7. 0
    Esmaeil Fadaei ·

    hi allPrimavera 7.0Error

    hi all

    Primavera 7.0

    Error while Removing WBS

    DB : SQL

    Error :

    an application event has been intercepted. please note the event code for reference 

    Event code  : DSEIS-2129-2

  8. 0
    Zoltan Palffy ·

    esmaeil fadaeido not steal

    esmaeil fadaei

    do not steal someones elses thread create a new post and it will be answered this way others can search for this same problem and the solution.  
  9. 0
    Toni Lupu ·

    Primavera 19.1.2Error while

    Primavera 19.1.2

    Error while scheduling

    DB : SQL

    Error :

    an application event has been intercepted. please note the event code for reference 

    Event code  : SSFII-0822-6  

    What' the explanation ?  How it is affecting the results ?

  10. 0
    Zoltan Palffy ·

    TONI LUPIyou have lops i your

    TONI LUPI

    you have lops i your schedule 

    Follow steps below to fix the issue:
    1. Click F9 to get the Schedule window.
    2. Check the Log to file option to save schedule details.
    3. Schedule the project.
    4. View the log, then fix the loops reported in the log file.

    Workaround:

    By default P6 only checks 10 loops per schedule.In order to allow more loops in the project, set a PM.ini named MaxLoopsToReportCount under Schedule option and set it value which suits the required loops.  It should not be too much so that schedule will take time to process so many loops.

    [Schedule]
    MaxLoopsToReportCount=-1 (this setting will show all loops)

Log in or join to reply