Resource Lag Duration

Izam ZakariaMember for 20 years 4 months
Created
1
4
0
In P3 software we call "Resource Lag Duration". But what we call it in P6? Did we’ve other specific name?

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    "Lag"

    Out of P6 Hint Help:
    "The time lag of the relationship. This is the time lag between the predecessor activity’s start or finish date and the successor activity’s start or finish date, depending on the relationship type. The time lag is based on the successor activity’s calendar. This value is specified by the project manager and is used by the project scheduler when scheduling activities."