Adjusting The Histogram Legend

Anthony CaponeMember for 17 years 7 months
Created
2
3
0
I have renamed the budgeted Nonlabour unit’s column to represent tonnages. Unfortunately when I am in the Activity usage profile the legend in the histogram still show’s Nonlabour units.

My question is can you to rename the legend in the Histogram? So I can have it say Tonnage instead of Nonlabour units.

I am using P6.

Thanks in advance

2 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Anthony,

    First of all, WELCOME to Planning Planet.

    Yes, you can rename the column. However, you cannot rename the legend when you are using the "Activity Usage Profile", you can only rename the Nonlabor to Tonnage when you are going to use the "Resource Usage Profile"

    Follow the steps below:

    1. Go to View --> Show on Bottom --> Resource Usage Profile.
    2. Right click & select Stack Histogram, at right bottom corner of your screen, double click.
    2. In "Resource Usage Profile Option", under Data Tab, select ADD.
    3. In "Filters", rename the Filter Name into "TONNAGE" & select the parameters:
    where "Resource Type" equals "Nonlabor"
    4. Then select ok then apply.

    HTH.

    Regards,

    Arnold


  2. 0
    Anthony Capone ·
    Hi Arnold,

    And thank you for your responce. I didn’t think I would be able to change the Legend title but was not shore. Thanks again.