Guys i need a little help, i cannot locate my p6 files in my Hard drive, i wanted compress (zip/rar) some projects as to have it my flash drive as a back-up. Can somebody help me in this small problem.

Thanks in advance everyone!

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Ruel,

    Did you export your .XER file from P6? If not, you need to perform this prior to locate your .xer file to your hard drive. Then you can zip afterwards.

    To export your .xer file, open first the project and go to menu File --> Export --> Export Type, Primavera PM/MM-(XER) then next, in File Name: Locate the .xer file in your hard drive.

    HTH.

    Regards,

    Arnold
  2. 0
    Kyung-Hoon Ryu ·

    You can back-up entire SQL Database.

    Run SQL Server Management Studio Express and Back-up
    PMSB$PRIMAVERA.
    Then You can restore DB on another Computer.
    You can use all saved layout.
  3. 0
    Ruel Camaquin ·
    Thanks Guys! Both tips works!

    Ruel