Simple P6 Question
- Created
- 3
- 2
I'm sure this must be really simple to do in P6 but I can't work out how!
I have a task that is % Complete Type Duration, Task Dependent, and Fixed Duration and Units
It is a task which has started and must end on the 17 September 2012
I have set the Finish to Mandatory Finish of 17 September
When I schedule my plan, I want Primavera to automatically progress the % complete of this task when I change the data date
At the moment, when I schedule, it changes the end date even though it is set to Started and Mandatory Finish
Do I need to set an option somewhere to automatically update this task? I don't want to just do Update Progress as this will change all of my other tasks too.