P6 : Period Actual Line on S-Curve Profile

Bobby CunninghamMember for 21 years 2 months
Created
3
2
0
Hello all,
Question 1:
Is there a way to show the ’actual this period’ line only up to the current data date line instead of continueing straight across the profile to the Y-axis.
Question 2:
How do I show percentage values instead of manhours on the Y-axis.

I look forward to your replies.
Regards.

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Bobby,

    1. Use the Activity Usage Profile instead of Resource Usage Profile, and select labor, nonlabor, materials, expenses or total.

    You can also use the Tracking.

    2. First, check the Total Manhours of your project. Let say, 1,000,000 manhours.

    Go to Resource Usage Profile or Activity Usage Profile, then at the lower right corner of your screen or in the Histogram & Curve workspace, right click and select profile option.

    In the Graph Tab, tick the "Calculate Average" under the "Divide interval totals by:" write the 10,000 instead of 1,000,000 manhours. You need to divide it by 100.

    Under the "Unit of Measure:" Put the "%" symbol.

    Finally, go to edit --> User Preferences, Time Units Tab, tick the "Show Unit Label".

    HTH.

    Regards,

    Arnold

  2. 0
    Bobby Cunningham ·
    Arnold,

    Thanks a million for your assistance.

    Been a wee while since I worked with P6 and therefore a wee bit rusty.
  3. 0
    Arnold Puy ·

    You are Welcome Bob.