Resource Levelling with no Mandatory Lag

David KellyMember for 21 years 11 months
Created
2
2
0
Resource levelling and mandatory lag

Example:

A work instruction becomes an activity in P6.

Work instruction “a” is an isolation of a piece of equipment.

Work instruction “b” is the work to be performed when the isolation has been performed.

It is essential that the work is performed immediately after the isolation is performed.


A finish-to-start relationship does this very well when scheduling. Unfortunately since there is no “mandatory lag” capability in P6, when the project is levelled, there is no way to ensure that activity “b” follows immediately after activity “a”.

Any Ideas team?

2 replies

Oldest first
  1. 0
    Mark M ·
    Hi David

    I would suggest trying different combinations with the "levelling priorities". It may take some time to get the result you’re after as altering these priorities can give significantly different results...

    Alternatively you could add a unique resource to “work instruction b” & uncheck the “level all resources box”, then select all other resources except the unique resource.

    I’d be interested in others ideas on the subject...

    Regards
    Mark
  2. 0
    David Kelly ·
    Played with priorities until we are exhausted...

    The "unique resource" solution does not help us with this, as we do have to produce a plan that levels all the required resources.

    Of course it is NO HELP AT ALL to remember that P3 let you level with a filter, and that two or three passes with the leveller sorted this.