Open End Activity

Shahzad AhmadMember for 18 years 8 months
Created
6
2
0

Dear All

Problem related to P6

How i can find out open end activity in Log file.

in logic.... it is not clear at all.

Thanks
Shahzad

6 replies

Oldest first
  1. 0
    Arnel Lagumbay ·
    Shahzad

    Try to tick the"log to file" when you schedule your

    programme,there you can find activities w/o

    predecessors&successors.

    Hope this help..


    Best regards,
    arnel
  2. 0
    Rob Kane ·
    If you are looking for open ends, stick in your predecessor &successor columns in a layout and run a filter where they = "null"

    Rob
  3. 0
    Shahzad Ahmad ·
    Hi Rob

    Thanks for reply i found them.


    Thanks
    Shahzad
  4. 0
    Mangesh Khuspe ·

    Dear Shahzad, There is also

    Dear Shahzad,

     

    There is also another way for that which Rafael and Gary have suggested and can be found at

    http://www.planningplanet.com/forums/primavera-version-pm5-pm6/503663/open-link-activity

     

    WIth Regards,

     

    Mangesh 

  5. 0
    Irfan Khan ·

    hi,  run ur project with data

    hi, 

     

    run ur project with data date press F9 Press View Log & under SCHEDLOG.notepad u can see Errors:

    Warnings: u can find here (Activities without predecessors) (Activities without successors) (Out-of-sequence activities)

    (Activities with Actual Dates > Data Date) (Milestone Activities with invalid relationships) etc.

    hope it ill be helpfull....

     

    regards,,,,
     

  6. 0
    Jenn Weber ·

    You could also try using the

    You could also try using the logic analyzer in Acumen Fuse to find all open ended activities (as well as leads, lags, out of sequence activities, reverse logic, redundant, and other logic flaws) within your schedule or in multiple linked schedules.  Visit our website for more information or a free trial of the software: http://www.projectacumen.com/fuse/overview/analysis 