P6 Budget cost actuals
In the Open Standard
Kevin MarkhamMember for 19 years 5 months
- Created
- 4
- 2
0
Can anyone help with the following. I have a baselined schedule which gets updated every week. Whenever I change % complete and current finish date for an activity my previous actuals, remaining and at complete budget costs disappear and reset to zero. On some activities even the budgeted labour cost resets to zero. Also can the actual labour cost be linked to % complete so it works out the number itself.
Thanks
Thanks
4 replies
Oldest firstLog in or join to reply