P6 Budget cost actuals

Kevin MarkhamMember for 19 years 5 months
Created
4
2
0
Can anyone help with the following. I have a baselined schedule which gets updated every week. Whenever I change % complete and current finish date for an activity my previous actuals, remaining and at complete budget costs disappear and reset to zero. On some activities even the budgeted labour cost resets to zero. Also can the actual labour cost be linked to % complete so it works out the number itself.

Thanks

4 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Kevin,

    The reason why the actual qty/cost set to zero it is because:

    1. The Remaining Duration is equal or greater than Original Duration.
    2. The "Recalculate Actual Units & Cost when duration % complete changes" in Project Detail --> Calculation Tab.

    Untick the mark next to "Recalculate Actual Units & Cost when duration % complete changes". And put the Actual Units manually.

    Hope this helps.

    Regards,

    Arnold



  2. 0
    Kevin Markham ·
    Thanks that helped. Another problem I am having is when I dump down my actual costs from one of the reports into excel on a weekly period after updating and analysing my schedule. P6 changes all the previous weeks data making my actual history curve change each week. If I just take the last period and ignore the rest and put that into my excel sheet the cummulative value/percent doesn’t match the plan and CSV files cummualtives ?
  3. 0
    Arnold Puy ·
    Hi Kevin,

    Everytime you will update weekly, your actual units/cost will change when you did not untick the "Recalculate Actual Units and Cost when duration % complete changes".

    Perform "Store Period Performance" every week. You can track actual units and costs to date each time the schedule is updated.

    You can edit the data in financial period columns of the Activity Table, Resource Assignments window, and the Resources tab of Activity Details.

    Hope this helps.

    Cheers,

    Arnold
  4. 0
    Ahmed Farag ·

    Hi;Can anyone help with the

    Hi;

    Can anyone help with the following.

    My previous actual units changes everytime I update (Schedule Project). I'm Sure I Untick the mark next to "Recalculate Actual Units & Cost when duration % complete changes" at project level.

    note:- the actual changes to be linear change (for ex. if actual units are 24 for 4 periods each period changes to be 6 units)

Log in or join to reply