Critical Path P6
In the Open Standard
Ben HallMember for 18 years
- Created
- 11
- 2
0
Gents,
I have an issue, my schedule is not picking up the critical path.
I can actually see where the critical path is on the schedule, but Primavera isn’t highlighting activities red on gannt chart.
Activities all have successor activity, waterfall style.
I have the scheduler on default setting.
Any ideas what is going wrong? My client it wondering why also.
I have an issue, my schedule is not picking up the critical path.
I can actually see where the critical path is on the schedule, but Primavera isn’t highlighting activities red on gannt chart.
Activities all have successor activity, waterfall style.
I have the scheduler on default setting.
Any ideas what is going wrong? My client it wondering why also.
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?