Importing from P3 to P6

Sanjay RaoMember for 18 years 4 months
Created
2
2
0
Hello
I need your help as i am facing following problem when i import file from P3 to P6 resource in p3 shows as nonlabour in P6 some resource is Nonlabour & Some are labour. How to resolve this problem

2 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Sanjay,

    Try to change the resource type from labor to nonlabor by filtering all activities having the resource type of labor. Afterwards, select the "Assign Resource" command button located at your right corner of your screen.

    Select the resource name and select replace then assign the new resource type (labor). This cannot be done for the activities that has already actual.

    Hope this helps.

    Regards,

    Arnold
  2. 0
    Sanjay Rao ·
    Hello Arnold
    Thanks