pct complete & RD unlink

Michael RamosMember for 17 years 8 months
Created
4
2
0
hi planners

how can i unlink % complete and remaining duration in p6, i will use it for just a few activities?



thanks

4 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Michael,

    Go to Project Detail --> Calculations Tab --> Under Resource Assignments, untick the "Recalculate Actual Units and Cost when duration % complete changes".

    Regards,

    Arnold
  2. 0
    Michael Ramos ·
    hi arnold,

    when i am changing duration % complete, remaining duration still changes.

    i already untick the option you posted below.

    my question is to unlink the duration % complete and RD.

    thanx again

  3. 0
    Arnold Puy ·
    Hi Michael,

    Try to use Physical % Complete. It is mnually user’s input.

    Regards.
  4. 0
    Ali Farhat ·
    I go for what Arnold said...