How to show activities to P6?
In the Open Standard
Jerry FernandezMember for 17 years 6 months
- Created
- 4
- 2
0
Dear All!
When I finished creating activities to P6, then i click all project then i go back to activities again it is not already displayed only were shown are the WBS. Can anyone tell me how to displayed all acitivity when i click activities?
I will appreciate all your answer.
Regards.
Jerry
When I finished creating activities to P6, then i click all project then i go back to activities again it is not already displayed only were shown are the WBS. Can anyone tell me how to displayed all acitivity when i click activities?
I will appreciate all your answer.
Regards.
Jerry
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?