Importing Time Clock Data
In the Open Standard
Milton MaindonaldMember for 19 years 3 months
- Created
- 9
- 1
0
Can somebody assist???
We have recently introduced a time clock system where resources time write to activities within the plan. On a weekly basis I update the % complete in the plan, and then import the actual data via an excel spread sheet and it populates the "Actual Hours".
Now here’s my problem: The Remaining Labor Units end up not representing the % complete, as in some cases the teams have spent too many hours etc. etc.
I need the Remaining Labor Units to balance as it affects my "At Completion Labor Units" and subsequently upsets my "Cost Performance Index - Labor Units".
Is there another setting within Primavera I have to change other than taking the tick out of the "Recalculate Actual Units and Cost when Duration % Complete Changes" box?
Cheers,
Milton.
We have recently introduced a time clock system where resources time write to activities within the plan. On a weekly basis I update the % complete in the plan, and then import the actual data via an excel spread sheet and it populates the "Actual Hours".
Now here’s my problem: The Remaining Labor Units end up not representing the % complete, as in some cases the teams have spent too many hours etc. etc.
I need the Remaining Labor Units to balance as it affects my "At Completion Labor Units" and subsequently upsets my "Cost Performance Index - Labor Units".
Is there another setting within Primavera I have to change other than taking the tick out of the "Recalculate Actual Units and Cost when Duration % Complete Changes" box?
Cheers,
Milton.
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?