View Log

Moutaz AldeibMember for 22 years 9 months
Created
3
2
0
Dear planners,

I’d like to show the schedule report but a message always says log file does not exist.

regards,

Moutaz

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Moutaz
    You should mark "create log-file".
    "F9" --> Mark "Create..." --> click on the "..." to create that file --> schedule --> View log will be available.

    Regards
    Dieter
  2. 0
    Billy Caraig ·

    Hi planners,I have the same

    Hi planners,

    I have the same problem, I checked "log to file" option but whenever I schedule the project it says "Log file cannot be created: C:\Program Files\Primavera P3ec for Construction\Project Manager\SchedLog.txt".. Please help> Thanks

  3. 0
    Ronald Winter ·

    You need to change the place

    You need to change the place where the log file is stored.  Ever since Vista operating system came out, one cannot save user files in the C:\Program File\... directories.  Good luck!