curves

Shahzad AhmadMember for 18 years 8 months
Created
2
2
0
Hi all

could any one explain me how to change the resource curves

my curves is not smoth i would like to assign early Peak

i try to assign it follow stpes.

Enterprise > resource curves> then i selected Early Peak

> modify ...Assign my curves not changed.

Thanks
shahzad




2 replies

Oldest first
  1. 0
    Michael Ridino ·
    Hi Shahzad,

    When you assign a resource to an activity you can add a column for which curve the resource should use. Enterprise > Resource Curves is where you go to modify or add a new curve. Early Peak is a Primavera default curve so you wont be able to modify it. Instead click add and use Early Peak as the curve to copy from.

    Mike
  2. 0
    Shahzad Ahmad ·
    Hello Mike

    Thanks for your reply.

    I got it.
    there is any option other then (global change)

    where i can change my existing resource curves with a new curves for Cummulative units.

    Thanks
    shahzad